HomeMy WebLinkAbout1519 KIRPATRICKIn Re: James Kirpatrick,
Respondent
File Docket:
X -ref:
Date Decided:
Date Mailed:
Before: Louis W. Fryman, Chair
Donald M. McCurdy
Paul M. Henry
Raquel K. Bergen
Nicholas A. Colafella
08 -022
Order No. 1519
7/8/09
7/10/09
This is a final adjudication of the State Ethics Commission.
Procedurally, the Investigative Division of the State Ethics Commission conducted
an investigation regarding possible violation(s) of the Public Official and Employee Ethics
Act ( "Ethics Act "), 65 Pa.C.S. § 1101 et seq., by the above -named Respondent. At the
commencement of its investigation, the Investigative Division served upon Respondent
written notice of the specific allegation(s). Upon completion of its investigation, the
Investigative Division issued and served upon Respondent a Findings Report identified as
an "Investigative Complaint." An Answer was filed and a hearing was waived. The record
is complete.
This adjudication of the State Ethics Commission is issued under the Ethics Act and
will be made available as a public document thirty days after the mailing date noted above.
However, reconsideration may be requested. Any reconsideration request must be
received at this Commission within thirty days of the mailing date and must include a
detailed explanation of the reasons as to why reconsideration should be granted in
conformity with 51 Pa. Code § 21.29(b). A request for reconsideration will not affect the
finality of this adjudication but will defer its public release pending action on the request by
the Commission.
The files in this case will remain confidential in accordance with the Ethics Act.
Kirkpatrick, 08 -022
Page 2
I. ALLEGATIONS:
That James Kirkpatrick, a (public official /public employee) in his capacity as
Transportation Facilities Administrator I violated the following provisions of the State Ethics
Act (Act 93 of 1998) when he used the authority of his public position for a private
pecuniary benefit by directing that contractors for the Department of Transportation
provide personal items to him at no cost at a time when he was reviewing and approving
contracts for vendors who provided him with items used for his personal purposes; when
he failed to file a Statement of Financial Interests for the 2007 calendar year by May 1,
2008; when he failed to disclose all direct /indirect sources of income on Statements of
Financial Interests filed for 2004 and 2005 calendar years; and when he failed to disclose
the identity of all creditors on a Statement of Financial Interests filed for the 2006 calendar
year.
§ 1103. Restricted activities
(a) Conflict of interest. —No public official or public
employee shall engage in conduct that constitutes a conflict of
interest.
65 Pa.C.S. § 1103(a).
§ 1104. Statement of financial interests required to be
filed
(a) Public official or public employee. —Each public
official of the Commonwealth shall file a statement of financial
interests for the preceding calendar year with the commission
no later than May 1 of each year that he holds such a position
and of the year after he leaves such a position. Each public
employee and public official of the Commonwealth shall file a
statement of financial interests for the preceding calendar year
with the department, agency, body or bureau in which he is
employed or to which he is appointed or elected no later than
May 1 of each year that he holds such a position and of the
year after he leaves such a position. Any other public
employee or public official shall file a statement of financial
interests with the governing authority of the political
subdivision by which he is employed or within which he is
appointed or elected no later than May 1 of each year that he
holds such a position and of the year after he leaves such a
position. Persons who are full -time or part -time solicitors for
political subdivisions are required to file under this section.
65 Pa.C.S. § 1104(a).
§ 1105. Statement of financial interests
(b) Required information. —The statement shall
include the following information for the prior calendar year
with regard to the person required to file the statement:
(4) The name and address of each creditor to
whom is owed in excess of $6,500 and
the interest rate thereon. However, loans
or credit extended between members of
the immediate family and mortgages
Kirkpatrick, 08 -022
Page 3
(5)
securing real property which is the
principal or secondary residence of the
person filing shall not be included.
The name and address of any direct or
indirect source of income totaling in the
aggregate $1,300 or more. However, this
provision shall not be construed to
require the divulgence of confidential
information protected by statute or
existing professional codes of ethics or
common law privileges.
65 Pa.C.S. § 1105(b)(4) -(5).
§ 1102. Definitions
"Conflict" or "conflict of interest." Use by a public
official or public employee of the authority of his office or
employment or any confidential information received through
his holding public office or employment for the private
pecuniary benefit of himself, a member of his immediate family
or a business with which he or a member of his immediate
family is associated. The term does not include an action
having a de minimis economic impact or which affects to the
same degree a class consisting of the general public or a
subclass consisting of an industry, occupation or other group
which includes the public official or public employee, a
member of his immediate family or a business with which he or
a member of his immediate family is associated.
65 Pa.C.S. § 1102.
II. FINDINGS:
Pleadings
1 The Investigative Division of the State Ethics Commission received information
alleging that James Kirkpatrick violated provisions of the State Ethics Act (Act 93 of
1998).
2. Upon review of the information the Investigative Division initiated a preliminary
inquiry on April 1, 2008.
3. The preliminary inquiry was completed within sixty days.
4. On May 28, 2008, a letter was forwarded to James Kirkpatrick by the Investigative
Division of the State Ethics Commission informing him that a complaint against him
was received by the Investigative Division and that a full investigation was being
commenced.
a. Said letter was forwarded by certified mail, no. 7007 0220 0001 4375 2952.
b. The domestic return receipt bore the signature of James Kirkpatrick, with a
delivery date of May 30, 2008.
5. On September 5, 2008, the Investigative Division of the State Ethics Commission
Kirkpatrick, 08 -022
Page 4
filed an application for a ninety day extension of time to complete the Investigation.
6. The Commission issued an order on September 22, 2008, granting the ninety day
extension.
7 On November 12, 2008, the Investigative Division of the State Ethics Commission
filed an application for a second ninety day extension of time to complete the
Investigation.
8. The Commission issued an order on December 4, 2008, granting the ninety day
extension.
9. On March 26, 2009, an amended Notice of Investigation was forwarded to James
Kirkpatrick by the Investigative Division of the State Ethics Commission informing
him that the allegations contained in the May 28, 2008, Notice of Investigation were
being amended.
a. Said letter was forwarded by certified mail, no. 7006 2150 0002 5372 6840.
b. The domestic return receipt bore the signature of C. Kirkpatrick, with a
delivery date of March 30, 2009.
10. Periodic notice letters were forwarded to James Kirkpatrick in accordance with the
provisions of the Ethics Act advising him of the general status of the investigation.
11. The Investigative Complaint /Findings Report was mailed to the Respondent on May
14, 2009.
12. James W. Kirkpatrick, Jr. was employed as a Transportation Facilities Administrator
1 with the Facilities Management Division (hereafter FMD), Bureau of Office
Services, Deputate of Administration, Pennsylvania Department of Transportation
(hereafter Department) from approximately July 13, 1999, through January 3, 2008.
a. Kirkpatrick also held the following positions with the Department at various
points over the time frame of August 1989 to July 1999 before his promotion
to the position of Transportation Facilities Administrator 1:
1. Engineering Technician;
2. Bridge /Structural Design Technician;
3. Bridge /Structural Drafter;
4. Electrical Construction Inspector;
5. Transportation Construction Inspector Supervisor;
6. Transportation Construction Inspector Supervisor /Electrical
Construction Inspector; and
7. Roadway Programs Specialist.
b. Kirkpatrick's employment with the Department was not consecutive from
1989 to 2008.
1. Kirkpatrick was not employed with the Department from September
19, 1997, through January 24, 1999.
Kirkpatrick, 08 -022
Page 5
c. Kirkpatrick submitted e-mail correspondence dated January 4, 2008,
expressing a desire to separate from his regular status position as a
Transportation Facilities Administrator I (hereafter TFA I).
d. The Department accepted Kirkpatrick's resignation via letter dated January
18, 2008.
13. The Department's position description [for] the TFA I (a /k/a District Facilities
Manager) for Engineering Districts 11 -0 and 12 -0 defines the position purpose as
participation in the planning, assigning, directing, and coordinating of services
associated with building design, maintenance, construction, and repair for all
facilities within Transportation Engineering District 11 -0 and 12 -0 and notes, in part,
the following duties and responsibilities:
a. Maintenance and management of district four -year facilities plans; and
budgets and ensures funding is spent wisely and effectively provides reports
as needed;
b. Planning and coordinating of services associated with building maintenance,
design construction, and repair district wide;
c. Performance and monitoring of data entry and updates to the facilities
database as well as effective use of the database to ensure timely project
delivery;
d. Development of specifications and scope of work for facilities projects and
services;
e. Development and completion of initial contract bid documents and
associated ITQ contract requirements involved in the competitive bidding
process and ensures accuracy of all submissions;
f. Direction of the preparation of facility design, construction, renovation, and
demolition projects with input from agency consultative staff;
Scheduling and conduction of required project management meetings,
including pre -bid, pre -job, interim job, final inspection, and other meetings as
required;
h. Conduction of inspections of project work sites and ensuring contractor
compliance and performance in accordance with contract specifications and
scope of work; and
Evaluation of project status and percentage of completion; processing of
contractor invoices and associated departmental forms required for payment
of invoices in a timely manner.
g.
14. The FMD is part of the Bureau of Office Services, Deputate of Administration, of the
Department.
a. The FMD is responsible for providing technical support and infusion of
money into individual districts and counties regarding new construction,
building maintenance and remodeling, emergency repairs, paving, etc.
b. Buildings supported by the FMD include, but are not limited to, employee
staging areas, salt storage buildings (a /k/a huskies), roadside rest stations,
Kirkpatrick, 08 -022
Page 6
county /district offices, weigh stations, driver's license centers, etc.
15. The Commonwealth is divided into four separate regions (Northern, Southern,
Eastern, and Central) regarding FMD operations.
a. Each region was overseen by a TFA 111 and was composed of specific
Department districts during Bolinger's tenure with the exception of the
Central region as shown below:
Northern Southern Eastern Central
District 1 District 8 District 4
District 2 District 9 District 5
District 3 District 11 District 6
District 10 District 12
Note: Represents regional /district alignment prior to Bolinger's separation.
1. The Central region primarily addresses the administration of the FMD
and is not composed of specific districts.
aa. The Central region is based in Harrisburg, Pa.
2. Each district is overseen by a TFA 1 or 11 (a /k/a District Facility
Administrator) and is composed of various counties.
16. Craig Bolinger was assigned oversight of the Southern Region for the FMD in his
position as a TFA 111.
a. Counties composing the four districts in the Southern Region were as
follows:
District 8 District 9 District 11 District 12
Franklin Somerset Beaver Westmoreland
Adams Cambria Allegheny Washington
Cumberland Blair Greene
Perry Huntingdon Fayette
Dauphin Fulton
Lebanon Bedford
York
Lancaster
Note: Represents regional /district alignment prior to Kirkpatrick's
separation.
1. Emmanuel Walker was the TFA assigned to District 8.
2. Jack Rice was the TFA assigned to District 9.
17. Kirkpatrick reported to Bolinger as his immediate supervisor.
a. Kirkpatrick and Bolinger worked from the same office location at the
Engineering District 11- 0/12 -0 compound.
b. Kirkpatrick was the TFA assigned to Districts 11 and 12.
1. Kirkpatrick was initially assigned only District 11 but was assigned
District 12 upon Bolinger's promotion to the Southern Regional
Kirkpatrick, 08 -022
Page 7
Facilities Administrator.
2. Bolinger served as the District Facilities Administrator for District 12
prior to his promotion.
18. The FMD operates as a management /supervisory arm to ensure that Department
projects undertaken are completed per the documented project scope,
specifications, etc.
a. The FMD has no laborers or field employees with the exception of Regional
and District Facility Administrators.
b. The majority of construction work which is managed by the FMD is
performed under contract by an outside vendor.
19. The Department has invited contractors to respond to an Invitation To Qualify (ITQ)
for Facility Construction, Renovation, and Inspection Services since at least
October 24, 2001.
a. The ITQ is assigned an actual contract number under which a specific scope
of work may be completed.
1. From at least October 24, 2001, through December 31, 2005, the ITQ
for FMD related projects /services was documented under Contract
Number 359002.
2. From approximately January 1, 2006, through December 31, 2011,
the ITQ for FMD related projects /services has been /will be
documented under Contract Number 354102.
b. The ITQ documents qualification requirements, contract terms and
conditions, special requirements and specifications, service type and
location information, etc., via various exhibits (i.e. Exhibit A, Exhibit B, etc.).
20. In order to qualify for the ITQ program, interested contractors are required to
complete the contractor's signature page of the ITQ as well as any specific Exhibits
as documented in the ITQ Table of Contents and return the documents to the
Department's Bureau of Office Services located in Harrisburg, Pa.
a. The ITQ requires that contractors complete a Service Type and Location
Sheet on which the contractors identify the following:
1. Company or individual name and Federal Identification or Social
Security Number;
2. The services the company or individual wishes to provide
distinguished by category and sub - category (i.e. Architectural:
General, Roofing, Windows, Doors, etc.; Mechanical: Heating /Air
Conditioning, Plumbing, etc.; Inspection Services: General, Roofing,
Masonry /Concrete, etc.).
3. The County /Counties where the company or individual wishes to
provide services.
21. Contractors meeting all qualification requirements as contained in the ITQ are
awarded a contract and added to the Department's list of approved contractors.
Kirkpatrick, 08 -022
Page 8
a. Being qualified as an approved contractor on the ITQ does not guarantee
the awarding of projects to the contractor under the ITQ contract number.
1. Being qualified as an approved contractor on the ITQ guarantees only
the opportunity to bid on projects that require competitive bidding.
22. Projects planned by the FMD are governed by cost thresholds established by the
PennDOT Procurement Manual and the Department of General Services Field
Procurement Handbook.
a. Cost threshold information is also documented in the ITQ in effect at the time
of the project.
23. The ITQ under Contract Number 359002 noted cost thresholds in effect under
Exhibit C — Special Requirements and Specifications, Sections 1 (General) and 2
(Procedure).
a. Section 1 documented that services provided must cost less than
$100,000.00 per project including both materials and labor.
1. All aviation projects, except vertical construction projects, were
exempt from the dollar limit.
b. Section 2 documented that any project costing less than $3,000.00 did not
require competitive bidding.
c. Section 2 documented that any project totaling over $3,000.00 including
materials and labor required the invitation of a minimum of three contractors
pre - qualified in the service type and county where the work was to be
performed to bid on the project.
24. Any project requiring services, including both labor and materials, which totaled
between $10,000.01 and $100,000.00 required the following of the competitive bid
process.
a. Any services /project totaling more than $100,000.00 required a Delegation
from the Department of General Services in order for the Department to
maintain control of the project.
1. The Department was specifically issued a Delegation from the
Department of General Services, Bureau of Engineering and
Architecture on December 2, 2003, relating to the design, bid, and
construction of salt storage buildings with construction cost estimates
not exceeding $500,000.00.
2. The Delegation granted for salt storage buildings was specifically
incorporated into the ITQ under Contract Number 354102.
25. The ITQ under Contract Number 354102 also noted cost thresholds in effect under
Exhibit C — Special Requirements and Specifications, Sections 1 (General) and 2
(Procedure).
a. Section 1 documented that facility projects, including both materials and
labor, must not exceed $100,000.00 per project and salt storage buildings
must not exceed $500,000.00 per project.
1. All aviation projects, except vertical construction projects, were
Kirkpatrick, 08 -022
Page 9
exempt from the dollar limit.
b. Section 2 documented that any project costing less than $3,000.00 did not
require competitive bidding.
1. Although not documented on the ITQ, currently any project totaling
less than $5,000.00 does not require competitive bidding.
c. Section 2 documented that any project totaling over $3,000.00 including
materials and labor required the invitation of a minimum of three contractors
pre - qualified in the service type and county where the work was to be
performed to bid on the project.
1. Although not documented in the ITQ, the current cost threshold for a
minimum of three quotes is set at $5,000.00.
26. Any project requiring services, including both labor and materials, which totaled
between $10,000.01 and $100,000.00 required the following of the competitive bid
process.
a. Any project totaling more than $100,000.00 required a Delegation from the
Department of General Services in order for the Department to maintain
control of the project.
27. Exhibit C — Special Requirements and Specifications of the current ITQ and the
prior ITQ both include a provision on contractor performance.
a. Contractors who perform poor work, do not provide services on time, or
engage in other unacceptable conduct are to be entered into the
Commonwealth's Contractor Responsibility Program (CRP).
1. The purpose of the Contractor Responsibility Program is to ensure
that the Commonwealth contracts only with responsible contractors
and that the Commonwealth collects any obligations owed to it
through offset review as documented in Management Directive 215.9
(amended).
2. "Other unacceptable conduct" is not defined in the past or current
ITQ.
b. Entries into the Contractor Responsibility Program may be considered in
determining whether to exclude a contractor from award of assignments
under the ITQ and may lead to termination of a Contractor's Contract.
28. Projects to be undertaken by the FMD within the four geographical regions of the
Commonwealth are primarily determined via the development of a four -year plan for
each District in each respective region.
a. Four -year plans are normally generated by the DFA with the assistance of
the County Manager from each county which composes the District.
b. Four -year plans identify what the DFAs and County Managers desire to
accomplish in the next four years relating to new construction, remodeling,
etc.
1. Although developed for a four year period, the plans are constantly in
a state of flux as a result of unplanned situations (i.e.
Kirkpatrick, 08 -022
Page 10
emergency /unexpected repairs, maintenance, etc.).
c. Once compiled, the four year plans are presented to the RFA for review and
input.
29. The RFAs subsequently attend a budget meeting at the Bureau of Office Services
central office in Harrisburg, PA with the Division Chief of the FMD to request a
dollar amount regarding funding for the projects identified.
a. The Division Chief subsequently allocates a lump sum funding figure to each
RFA's region.
1. The RFA determines the amount of funds to be allocated to each
district for upcoming projects.
2. Projects to be completed are prioritized based on available funds.
30. The general process by which an FMD project is created and bid is accomplished
through a multi -step procedure as detailed below:
a. Determination of the need for the project by the applicable DFA who then
consults with the applicable RFA.
b. Initial "building" of the project by the DFA via entry into the Penn State
Facilities Engineering Institute database if the cost estimate is under
$100,000.00 (based on prior projects, cost familiarity, etc.).
1. Initial building of the project requires the entry of a general scope of
work and estimated cost for the project.
c. Once entered, the database generates and assigns an FM Number
(sequentially) to the project and sends an e-mail to the RFA to approve the
project.
1. The e -mail documents the funding source for the project, what the
project is, etc.
d. Once the RFA approves the project, an e-mail documenting the approval is
sent back to the DFA.
e. After receiving approval from the RFA, the DFA continues to build the project
via step -by -step entry fields in the database including but not limited to
specifications, prevailing wage information, pre -bid meeting date, bid due
date, routing slip information, submission to Graphics, etc.
1. Entry of the routing slip information informs the FMD purchasers at
the Central Office to send the bids to all applicable contractors on the
ITQ, the DFA, and the RFA.
2. Submission to Graphics indicates that the project has been submitted
to Graphics and that all information entered by the DFA, including
contractor names from the ITQ, is correct as verified by the
purchaser.
f. Graphics prints all of the required project information for each contractor
identified and supplies it to the purchaser who subsequently mails the actual
packet to the contractors.
Kirkpatrick, 08 -022
Page 11
1 The packet provided includes a pre -bid meeting response document,
a bid sheet, and project identification (i.e. scope of work,
specifications, etc.).
aa. The pre -bid meeting response document identifies the time
and place of the pre -bid meeting as well as if the pre -bid
meeting is or is not mandatory.
1. All pre -bid meetings are currently mandatory.
bb. The pre -bid meeting response document is typically faxed to
the DFA and serves as notification regarding those contractors
planning on attending the meeting.
31. The DFA is required to attend the pre -bid meeting to provide clarification and
explanation of the project, answer questions on the project, and detail the scope of
work associated with the project.
a. The DFA is to take minutes of the pre -bid meeting to include the time, date,
those present, and notes of the meeting.
b. Any modification or change in the scope of work as a result of the pre -bid
meeting is required to be documented in the meeting minutes.
1. A written addendum of the changes is required to be provided to all
contractors present at mandatory pre -bid meetings and to the
applicable Purchasing Agent for inclusion in the project file.
aa. If the pre -bid meeting is not mandatory, the addendum must be
provided to all contractors invited to bid.
32. Contractors interested in the project must submit a written bid, based on the final
scope of work and any changes in specifications, with all required bid documents.
a. Bids are to be submitted on the bid sheet supplied in the project packet
distributed.
b. Bid[s] are to be submitted to the Purchasing Agents at the Bureau of Office
Services Central Office in Harrisburg, PA via fax, mail, electronic
transmission, or hand delivery prior to the specified due date.
1. The bid due date and time are specified on the bid sheet provided in
the project packet.
33. Once the bid deadline has passed, bids received are reviewed by at least two
Bureau of Office Services Purchasing Agents and the low bidder for the project is
determined.
a. Bids received are documented on a Summary of Bids form.
1. Information noted on the Summary of Bids includes all contractors
(name, address, and contact information) to which project packets
were distributed, actual bids submitted, the project (FM) number, the
bid opening time and date, and the signature of the witnesses to the
bid opening.
Kirkpatrick, 08 -022
Page 12
b. The Purchasing Agent assigned to the project subsequently issues a Notice
of Apparent Low Bidder to the contractor submitting the lowest bid.
1. The Notice of Apparent Low Bidder identifies the contractor name,
address, and number; the date issued; the project (FM) number; the
county, and district number.
34. The contractor in receipt of the Apparent Low Bid Notification is required to provide
various documents to the Department, including a performance bond, payment
bond, insurance certification listing the Commonwealth as additional insured,
recycled content product provision, and /or a steel origination certification.
a. If the information is not provided to the Department by the time and date
indicated on the Apparent Low Bid Notification, the contractor's bid may be
rejected.
35. Once the required documentation is received and reviewed by the Department, the
Purchasing Agent assigned to the project issues the Notice to Proceed to the
selected contractor.
a. The Notice to Proceed is the actual purchase order for the project.
1. No contractor can be paid for work completed without an approved
purchase order.
b. No work is to begin on the project until the Notice to Proceed has been
approved and issued.
36. A pre- construction conference is to be scheduled after the Notice to Proceed and
prior to the beginning of any actual work.
a. The DFA responsible for the project is required to be present at the pre -
construction meeting.
1. The RFA for the region in which the project is occurring may also be
present at the pre- construction meeting.
b. Attendance by the contractor or authorized representative is mandatory at
the pre- construction conference prior to the beginning of any work.
37. Progress meetings are to be scheduled throughout the progress of the work as
deemed necessary.
a.
The DFA responsible for the project is required to attend the progress
meetings.
1. The RFA for the region in which the project is occurring may also be
present at the pre- construction meeting.
b. The DFA or other Department representative may conduct periodic
unscheduled visits to the sight.
c. Contractors who perform poor work, do not provide services on time, or
engage in other unacceptable conduct are to be entered into the
Commonwealth's Contractor Responsibility Program.
38. A pre -final inspection is to be held two weeks prior to the termination date of the
Kirkpatrick, 08 -022
Page 13
project.
a. Items not completed regarding the project are to be placed on a punch list
and reviewed at that time with the contractor.
b. The contractor must complete all punch list items before the termination date
of the project.
c. A final inspection is to be performed at the end of the project period.
39. Once the project is complete, the DFA completes a goods receipt through SAP
which is sent to the Purchasing Agent via e -mail transmission.
a. Submission of the goods receipt through the SAP system signifies that the
required work is completed, the final inspection has occurred, and all work
was completed to required standards.
40. The Purchasing Agent subsequently matches the goods receipt to the purchase
order issued and forwards the purchase order and goods receipt to the
Comptrollers office.
a. The Comptroller matches the invoice received from the contractor to the
purchase order and goods receipt.
b. Once the triple match occurs (purchase order, goods receipt, and invoice),
payment due is authorized and released by the Comptroller's office.
41. Emergency work/repairs required for projects under the jurisdiction of the FMD do
not follow procedures established for small, no bid procurement (under $5,000.00)
or formal competitive sealed bids ([$10,000.01] to $100,000.00).
a. Procedure regarding emergency work/repairs includes:
1. Notification of the applicable RFA of the need for emergency
work/repairs.
aa. The applicable DFA is normally the individual who informs the
RFA of any emergency work/repairs required.
2. Obtaining of an Emergency Purchase Order Number from the
Harrisburg Central Office.
3. Completion of an Emergency Procurement Approval request by the
RFA (on behalf of Bureau Director) and forwarding of the request to
the Manager of Operational Services, Bureau of Procurement,
Department of General Services for approval.
4. Receipt of authorization to proceed with the Emergency Purchase
Order.
5. Entering the project into the Penn State Facilities Engineering
Institute database for assignment of a project (FM) number by the
DFA.
6. Generation of a scope of work required for the emergency
work/repairs by the DFA.
Kirkpatrick, 08 -022
Page 14
7 Solicitation of bids from at least three qualified contractors to perform
the work by the DFA.
aa. Contractors solicited are routinely those on the ITQ in effect at
that time.
8. Submission of bids by the contractors to the DFA at the DFA's office
and completion of a Summary of Bids for forwarding to the Central
Office.
9. Awarding the project by the Purchasing Agent to either the lowest
qualified bidder or the lowest qualified bidder first available to
complete the work.
10. Issuance of a purchase order (Notice to Proceed) for the project to
the DFA and the RFA.
11. Project completion and contractor payment.
b. There are no dollar value /threshold restrictions associated with emergency
purchase orders.
42. The Department maintains varying numbers of Stockpiles strategically located
throughout the counties which compose the separate districts in the
Commonwealth.
a. Stockpiles routinely have several structures on site which may include an
employee staging area, a materials storage area, parking sheds for vehicles,
a storage area for equipment and tools, etc.
43. On January 25, 2005, the Department issued project packets to various ITQ
qualified vendors which included an invitation to bid regarding Facilities Project
FM3221 and FM3222 under Contract No. 359002 to be located at the Searights
Stockpile in Fayette County.
a. The anticipated scope as documented on each invitation to bid called for the
construction of one 36'x45' Husky to be reimbursed by the Pennsylvania
Turnpike Commission.
1. The existing Department stockpile at Searights, PA was abandoned
by the Department as a result of an agreement between the
Pennsylvania Turnpike Commission and the Department.
aa. The Department agreed to relocate the Stockpile in order for
the Pennsylvania Turnpike Commission to extend a section of
Toll Route 43 (the Mon - Fayette Expressway).
bb. The Pennsylvania Turnpike Commission agreed to assist in
financing the relocation of the Stockpile.
b. The worksite for the projects was documented as, "Stockpile 22 District 12
Fayette County."
1. Stockpile 22 is located in Searights, Pa.
c. The pre -bid meetings for the projects were initially scheduled simultaneously
for February 28, 2005, at 10:00 a.m. at Stockpile 22.
Kirkpatrick, 08 -022
Page 15
1 Attendance at the pre -bid meeting was not mandatory.
2. An Addendum to the bid package dated January 28, 2005, amended
the pre -bid meeting for FM3221 and FM3222 to March 1, 2005, at
9:00 a.m. and 10:00 a.m. respectively.
d. Kirkpatrick was documented as the Department contact on each invitation to
bid
44. Clark Contractors, Inc. (hereafter Clark Contractors) was one of various vendors to
receive project information related to FM3221 and FM3222.
a. Clark Contractors is a general construction company located in Bedford, Pa.
b. Clark Contractors was approved to bid on facilities design, construction,
renovation and /or inspection work for the Department under Contract No.
359002.
1. Clark Contractors was an approved ITQ vendor.
45. Project information /specifications provided in the bid package specifically
documented the construction of salt buildings (Huskies) for the Searights Stockpile,
Fayette County, PA under FM3221 and FM3222.
a. Noted was that the projects were for construction between July 1, 2005, and
December 1, 2005, depending on the completion of site excavation.
46. Both Kirkpatrick and his immediate supervisor Craig Bolinger were present at the
pre -bid meeting held on March 1, 2005.
a. FM3221 and FM3222 as well as additional FM Numbers /projects to be
associated with the relocated Stockpile 22 were scheduled throughout the
day on March 1, 2005.
b. The pre -bid meeting verified that the construction was to occur at the new
location determined for Stockpile 22.
c. Site preparation for the new location had not yet been completed at the time
of the pre -bid meeting.
47. Purchase orders for various projects at the new Stockpile 22 location were
approved although the site for the projects had not yet been completed.
a. Purchase Order 4500215054 dated April 4, 2005, in association with
FM3221 was approved and awarded to lark Contractors in the amount of
$30,555.00.
1. Clark Contractors' bid of $30,555.00, submitted via facsimile
transmission to the FMD on March 17, 2005, was the lowest of four
bids received.
b. Purchase Order 4500217069 dated April 12, 2005, in association with
FM3222 was approved and awarded to Clark Contractors in the amount of
$29,200.00.
1. Clark Contractors' bid of $29,200.00, submitted via facsimile
Kirkpatrick, 08 -022
Page 16
transmission to the FMD on March 17, 2005, was the lowest of three
bids received.
48. Project information provided to contractors in the bid packages for FM3221 and
FM3222 specified that the Department was releasing the projects as "Design Build"
projects.
a. Design build projects are those in which the Department provides the
contractor with project specifications and the contractor is responsible for
designing the project.
b. The ultimate design is submitted to the DFA for approval upon completion.
49. Although change orders are addressed in the ITQ, specifically documented in the
explanation of "Design Build" as included in the bid packages issued for FM3221
and FM3222 is, "There will be no change orders on this project."
Change orders are addressed in the ITQ for Contract No. 359002 under
Exhibit C, Section 45, Advice of Change:
"If, due to unforeseen circumstances, work is uncovered which is necessary
for completion of the project, the Contractor shall submit to PennDOT, in
writing, a letter detailing the additional work. The work defined in the letter
must be within the original scope of work stated in the project specifications.
Upon acceptance, PennDOT will issue an Advice of Change to the Order for
the additional work. The Contractor shall not proceed with the additional
work until the Advice of Change is executed by all parties."
50. Due to the fact that the new site for Stockpile 22 was not ready for construction,
Bolinger approached Ronald Inks, Assistant County Manager, District 12 -1, Fayette
County, and questioned Inks if a salt storage building could be utilized at Stockpile
21, District 12, Fayette County, Dinnerbell, Pa.
a. Inks has supervisory responsibility over Stockpile 21 in his position as
Assistant County Manager.
1. Stockpile 21 is located in Farmington, Pa.
b. Bolinger also discussed additional modifications to Stockpile 21 with Inks.
1. Modifications to existing structures on site were discussed due to the
fact that two Huskies would not fit in the available space in the
stockpile compound.
c. Inks' approval for changes in the scope of work was not required.
51. Bolinger contacted Clark Contractors representative /estimator Clair Corle via
telephone regarding FM3221 and FM3222 after verifying that a new salt storage
building and other modifications could be utilized at the Dinnerbell Stockpile.
a. Bolinger informed Corle that the new Searights site was not ready.
b. Bolinger questioned Corle if he had any objection to constructing one salt
storage building and completing other renovations at the Dinnerbell
Stockpile instead.
a.
1. The scope of FM3221 did not change although the documented
Kirkpatrick, 08 -022
Page 17
location did.
2. Both the documented scope and location of FM3222 changed.
c. Corle did not object to the change in location for FM3221 or the change in
scope and location for FM3222.
52. Sometime after April 4, 2005, Bolinger confirmed the changes in scope to FM3222
via fax issued to Corle at Clark Contractors' office in Bedford, Pa.
a. The original fax sent to /received by Corle could not be located.
b. The fax sent to Corle changed the scope to account for electrical
service /lighting to an existing high arch salt storage building, lighting and
installation of a truck plow pad in an existing three bay salt storage building
(to be converted to truck parking), and installation of truck heaters as well as
the supply of an air compressor, pressure washer, and concrete saw.
1. The fax generated by Bolinger specified the make and model of the
air compressor, pressure washer, and concrete saw to be supplied.
53. Bolinger provided the list to Corle in order to determine if the new scope as
determined by Bolinger could be completed for the same amount ($29,200.00)
originally approved for FM3222.
a. Bolinger and Corle spoke several times regarding the changes as initial
estimates generated did not fall within the original amount approved for
FM3222.
1. Changes made included Bolinger's changing the specific
brands /models of equipment requested.
2. The brand names for the air compressor, pressure washer, and
concrete saw initially specified by Bolinger were more expensive than
the brands eventually agreed upon between Bolinger and Clark.
3. By Bolinger agreeing to accept less expensive brand names of
equipment, Clark was able to complete the project at the initial
$29,200.00 quote.
54. Although change orders were not authorized regarding design build projects under
Contract No. 359002, RFAs and DFAs had the authority to approve slight changes
in projects as long as the changes were in the same basic scope of the project and
no cost increase resulted from the change.
a. The ITQ requires that a change in a project location requires that a project
be cancelled and re -bid.
b. This project was authorized by Bolinger to move forward even though there
was a change of location from Stockpile 22 to Stockpile 21.
55. Clark Contractors representative Dick Clark purchased tools requested by Bolinger
in association with the revised scope of work under FM3222 at an approximate cost
of $2,658.47.
a. Clark purchased one 13 Horsepower Honda Concrete Saw with 18" guard,
Serial Number 01280265 from Pitt Industrial Diamond Products on October
Kirkpatrick, 08 -022
Page 18
20, 2005, in the amount of $2,161.34.
1. The $2,161.34 figure represents the cost of the saw and six percent
sales tax.
b. Clark purchased one Kobalt 22- gallon Digital Air Compressor Model No.
215914, Serial Number D19811299 from Lowe's Home Improvement
Warehouse.
1. The approximate value of the air compressor was $295.74 with sales
tax.
aa. Clark Contractors could not locate any receipt or payment
documentation for the purchase.
bb. The value of the air compressor was obtained from
jacksonville.travidia.com.
c. Clark purchased one Karcher Pressure Washer, Model No. K3.86, Serial
Number 387746.
1. The approximate value of the pressure washer was $201.39 with
sales tax.
aa. Clark Contractors could not locate any receipt or payment
documentation for the purchase.
bb. The value of the pressure washer was obtained from
deerso.com.
d. None of the tools Bolinger directed be purchased were needed in relation to
this project.
56. Tools purchased by Clark/Clark Contractors were delivered /transported to Clark
Contractors' main office in Bedford, PA.
a. Equipment purchased by Clark/Clark Contractors was purchased in the
same immediate time frame of mid - October 2005 to early November 2005.
57. Corle contacted Bolinger via telephone after obtaining the required equipment and
finishing work at the Dinnerbell Stockpile.
a. Corle advised Bolinger that the project was completed, that he had the
equipment required, and questioned if Bolinger wished for Corle to deliver
the equipment to the project site.
58. Bolinger declined Corle's offer to deliver the equipment to the Dinnerbell Site.
a. Kirkpatrick and Bolinger drove to Clark Construction in Bedford, PA on an
unidentified Friday and took possession of the equipment from Clark
Contractors.
b. Kirkpatrick and Bolinger drove to Clark Contractors' office in Bolinger's
Commonwealth provided vehicle.
1. Bolinger was assigned a Chevrolet pick -up truck (Equipment No. 094-
3030) by the Commonwealth in late October 2005 in his position as
Kirkpatrick, 08 -022
Page 19
an RFA.
59. Bolinger and Kirkpatrick subsequently returned to the District 12 -0 office location
with the equipment.
a. Although Bolinger and Kirkpatrick returned to their field office with the
equipment, the tools were not provided to any Department personnel for
custody or inventory purposes.
1. Bolinger did not notify or inform anyone at Engineering District 12 -0
or at Maintenance District 12 -1 of the equipment which had been
obtained.
b. No records could be located at Engineering District 12 -0 or at Maintenance
District 12 -1 documenting the delivery of the equipment.
60. Clark Contractors submitted an invoice (number illegible) dated October 25, 2005,
to the Department Comptroller's Office for payment in the amount of $30,555.00 for
services performed in association with FM3221.
a. The invoice referenced PO Number 4500215054.
b. The invoice description referenced "PO #: 4500215054 Project FM3221
36'x45' Storage Building."
61. Clark Contractors submitted an additional invoice number illegible) dated
November 9, 2005, to the Department Comptroller's Office for payment in the
amount of $29,200.00 for services performed in association with FM3222.
a. The invoice referenced PO Number 4500217069.
b. The invoice description referenced "PO #: 4500217069 Project FM3222
36'x45' Storage Bldg."
62. The invoice submitted by Clark Contractors for payment was not reflective of the
approved scope of work for FM3222 or the actual services performed in relation to
payment requested.
a. PO Number 4500217069/FM3222 documented approval for the construction
of a 36'x45' salt storage building at the Searights Stockpile.
b. Actual work performed included addition of electrical service and lighting to
existing structures, installation of a truck plow pad, and installation of truck
heaters at the Dinnerbell Stockpile location and equipment ultimately
provided to Bolinger by Clark Contractors which was not related to any
aspect of the project.
63. Clark Contractors submitted the invoice to the Department Comptroller's Office in
November 2005 at Bolinger's direction referencing completion of the original scope
of work at the original approved location rather than the actual services performed
and the equipment directed to be provided by Bolinger.
a. Clark Contractors submitted the invoice under the original scope of work
associated with the approved Purchase Order in order to receive payment
for services performed.
b. Payment to contractors cannot occur without an approved Purchase Order.
Kirkpatrick, 08 -022
Page 20
1. No Purchase Order was approved for repairs, upgrades, or additions
to the Dinnerbell Stockpile.
64. Clark Contractors received payment for services under FM3221 and FM3222 in the
original bid amounts of $30,555.00 and $29,200.00 respectively via Commonwealth
check number 09246736, dated December 16, 2005, in the amount of $59,755.00.
a. Payment received by Clark Contracting included payment for equipment
which Kirkpatrick and Bolinger took possession of from Clark Contracting.
b. Clark Contractors deposited Commonwealth check number 09246736 into its
business account at First American Bank on December 19, 2005.
65. The Department requires an annual inventory to be completed regarding equipment
and tools located at each Engineering and Maintenance District within the
Commonwealth.
a. The Department generally defines equipment as items which are operated to
complete a task and can move under their own power.
b. The Department generally defines tools as items which are used in order to
complete a task (i.e. hand tools, jacks, etc.).
c. The District Equipment Manager or his /her designee is responsible for
completing the inventory of the Engineering District Office while the County
Equipment Manager or his /her designee is responsible for completing the
inventory of County Maintenance Districts.
d. Inventories must be completed by May 15 annually.
66. Department equipment and tools are assigned specific numbers for identification
purposes and to ensure that equipment /tools purchased are actually on -site at their
assigned location.
a. Items identified as equipment bear a seven digit number stenciled on the
equipment in multiple locations.
1. Items identified as equipment originate from the Department in
Harrisburg and are provided with the equipment number already in
place.
b. Items identified as tools bear a four digit number which is engraved, written
in permanent marker, or noted on a brass tag which is affixed to the tool.
1. Tools purchased at the local level are marked with a sequential tool
number upon arrival.
67. Inventories conducted at Engineering Districts and County Maintenance Districts
are completed via the recording of equipment and tools by their applicable
equipment /tool number.
Any items discovered during the inventory process with no equipment /tool
number are to be noted on the inventory report and researched.
68. Inventories for Engineering District 12 -0 and Maintenance Districts 12 -1, 12 -2, 12 -4,
and 12 -5 were completed by Department personnel for 2005 -2006, 2006 -2007, and
a.
Kirkpatrick, 08 -022
Page 21
2007 -2008.
a. None of the inventories conducted documented the presence of the concrete
saw, air compressor, or pressure washer directed by Kirkpatrick and
Bolinger that Clark provide to them.
1. The inventories documented no tool number assigned to any of the
items received by Bolinger and Kirkpatrick.
2. The inventories documented no record of any concrete saw, air
compressor, or pressure washer discovered without a tool number
during the inventories.
69. Inventories conducted revealed the following tools of a similar nature present in
District 12 Maintenance districts as early as late winter /early spring 2005.
a. District 12 -1, Fayette County:
Item
15 HP Air
Compressor (2)
Pressure Washer
Pressure Washer
Concrete Saw
Item
Air Compressor (2)
Air Compressor
Compressor, Shop 15
HP
Concrete Saw, Hand-
held
Item
Pressure Washer
Pressure Washer (3)
Pressure Washer -Hot
Water
Pressure Washer
High Pressure
Washer
Air Compressor,
6HP60 Gal
Air Compressor,
6HP60 Gal (5)
Air Compressor
Make Tool No. Year Purchased Cost
Champion 0446/0447 1987 $5,000.00
NAPA
CAT
MK Diamond
b. District 12 -2, Greene County:
Make
Emglo
Hatfield - Campbell
Ingersol Rand
Stihl
c. District 12 -4, Washington County:
Make
Hurrican
Blador
Alkota
Blast Off
Hots Model 4400
Charge Air Power
Cambell Hausfield
Emglo
0133
0205
0761
Tool No.
0040/0288
0308
0389
0588/0599
1 Tool Number 0040 was labeled as an Emglo compressor on the
inventory completed in 2005 and as a Champion compressor on the
inventory completed in 2006.
Tool No.
0148
0493/0489
0488
0502
0528
0226
0578
0433/0437
0436/0435
0434
0088
1998
2002
2006
Year Purchased
Unknown
Unknown
Unknown
Unknown Unknown
Year Purchased
1996
1989
2002
2002
1996
1996
1964
$1,498.00
$1,850.00
$1,340.00
Cost
Unknown
Unknown
Unknown
Cost
$900.00
$900.00
$4,075.00
$1,500.00
$125.00
$480.00
$480.00
$433.00
Kirkpatrick, 08 -022
Page 22
d.
Portable Air
Compressor
Item
Senco
District 12 -5, Westmoreland County:
Compressor, 10 Ton
Air Compressor
Compressor
Air Compressor
Air Compressor
Pressure Washer
Ma
ke Tool
Ingersol Rand
Emglo- Lincoln
Emglot
Gardner Denver
Emglo
Troy Buict
70. Inventories conducted revealed the following equipment of a similar nature present
at the Engineering District 12 -0 main office as early as late winter /early spring 2006.
a. Engineering District 12 -0, Uniontown, PA, Fayette County:
Item Make
Concrete Saws (4) Stihl
0176 2001
Year
No. Purchased
0147 1977
0237 1980
0273 1981
0926 2003
0968 2005
0949 2004
Equipment Model
No. Year
090 -4759 1990
091 -4759 1990
122 -4759 1997
146 -4759 2001
Concrete Saw Blazer Diamond 195 -4968 1999
Cost
$1,700.00
$26.00
$1,900.00
$2,150.00
$2,000.00
$417.00
Acceptance
Date
08/10/90
08/10/90
08/11/97
07/20/01
04/29/1999
71. The Department has the ability to borrow tools from surrounding districts /counties
or purchase tools as needed in order to complete assigned tasks.
a. The Department follows established procedures in relation to the purchase
of equipment.
1. The Department does not solicit the FMD for provision of tools.
2. The FMD has no authority or responsibility to purchase or otherwise
obtain tools for the Department.
b. Bolinger's solicitation of the tools from Clark was contrary to Department
policies and procedures.
72. Bolinger was observed bringing the concrete saw, air compressor, and pressure
washer to the Engineering District 12 -0 Office in his Commonwealth issued vehicle
in or about April 2007.
a. Bolinger was suspended by PennDOT from his position in April 2007.
b. Bolinger questioned Donald Lowry, District 12 -0 Building Maintenance
Foreman, if the tools could be stored in the Lawn Maintenance Building.
1. The Lawn Maintenance Building is utilized to store large pieces of
district lawn maintenance equipment, tools, and general building
supplies.
$229.00
Kirkpatrick, 08 -022
Page 23
aa. The County occasionally stores items in the Lawn
Maintenance Building if necessary.
2. Lawn Maintenance Building keys were maintained by Lowry, Ronald
Jones - Maintenance Repairman 11, and an intern.
c. The appearance of the tools indicated that they had been used.
d. Lowry did not assist in removing the items from the truck for storage in the
Lawn Maintenance Building.
73. The tools were present in the Lawn Maintenance Building at the time of Kirkpatrick's
suspension from the Department in April 2007.
a.
b.
The tools were subsequently moved to the Dead Storage building located at
the Engineering District 11- 0/12 -0 compound.
The tools have remained in the Dead Storage building since that time.
74. During an interview with Commission investigators on March 12, 2009, Kirkpatrick
stated the following:
a. Several "gray areas" existed in FMD procedures which were not specific on
how projects were to proceed (including change orders).
b. Kirkpatrick was not intimately involved in the decision to move FM3221 and
FM3222 from the Searights location to the Dinnerbell location.
c. Kirkpatrick was not intimately involved in the decision to change the work
associated with FM3222.
d. Kirkpatrick was not involved in the decision to solicit tools from Clark
Contractors in association with FM3222.
e. Kirkpatrick did not utilize any of the tools obtained for any type of personal
use.
THE FOLLOWING FINDINGS RELATE TO ALLEGATIONS THAT KIRKPATRICK
FAILED TO DISCLOSE ALL DIRECT /INDIRECT SOURCES OF INCOME ON
STATEMENTS OF FINANCIAL INTERESTS FILED FOR CALENDAR YEARS 2004 AND
2005, THAT HE FAILED TO DISCLOSE THE IDENTITY OF ALL CREDITORS ON HIS
STATEMENT OF FINANCIAL INTERESTS FILED FOR CALENDAR YEAR 2006, AND
WHEN HE FAILED TO FILE A STATEMENT OF FINANCIAL INTERESTS FOR THE 2007
CALENDAR YEAR BY MAY 1, 2008.
75. Statement of Financial Interests filing requirements for public officials and public
employees are mandated by Section 1104 of the State Ethics Act.
a. Section 1104(a) specifies that each public employee or public official of the
Commonwealth must file an SFI for the preceding calendar year with the
department, agency, body, or bureau in which he is employed or to which he
is appointed or elected no later than May 1 of each year that he holds such a
position and of the year after he leaves such a position.
1. Kirkpatrick was required to file Statements of Financial Interests by
May 1 annually in his position as a DFA with the Department.
Kirkpatrick, 08 -022
Page 24
76. Section 1105(b) subsections 1 -10 document specific information which must be
noted on Statements of Financial Interests filed.
a. Section 1105(b)(5) requires the disclosure of any direct or indirect source of
income totaling $1,300.00 or more in the aggregate.
b. Section 1105(b)(4) requires the disclosure of each creditor owed in excess
of $6,500.00 and the interest rate in effect.
77. Statements of Financial Interests filed by Kirkpatrick as a public employee with the
Department were requested by the Investigative Division from Attorney Heather
Sharp, Assistant Counsel in Charge, Personnel Section, Office of Chief Council,
Department of Transportation via correspondence dated May 12, 2008.
a. Kirkpatrick's past five calendar years' Statements of Financial Interests were
requested beginning with the SFI filed in 2008 for calendar year 2007.
78. Statements of Financial Interests on file with the Department regarding Kirkpatrick
for calendar years 2002 through 2007 at the time of the request are dated as
follows:
Calendar Year Filing Date
2003 05/26/04
2004 04/20/05
2005 04/18/06
2006 04/10/07
2007 None
79. Kirkpatrick failed to disclose all direct /indirect sources of income on his SFI filed for
calendar year 2005.
a. Kirkpatrick was employed with Sony Technology of Pittsburgh from at least
October 20, 2004, through April 20, 2005.
b. Kirkpatrick did not disclose Sony Technology of Pittsburgh as a direct or
indirect source of income on his 2005 calendar year SFI.
1. Kirkpatrick disclosed income in the amount of $5,500.00 from Sony
Technology during the period of October 20, 2004, through April 20,
2005, on his Governor's Code of Conduct Statement of Financial
Interest.
80. Kirkpatrick failed to disclose the identity of his automobile creditor on his SFI filed
for calendar year 2006.
a. Kirkpatrick's SFI documents only "Auto Loan," "Bal. 9300.00," and "6.5"
(interest) under "Creditors" on his 2006 calendar year SFI.
b. Kirkpatrick did not document the actual name of the creditor or the address
of the creditor.
81. Kirkpatrick failed to file his 2007 calendar year SFI by May 1, 2008.
a. Kirkpatrick was made aware of his failure to file an SFI for calendar year
2007 by PennDOT representatives after PennDOT's receipt of the May 12,
2008, correspondence from the Investigative Division requesting to provide
Kirkpatrick, 08 -022
Page 25
copies of his Statements of Financial Interests.
b. Kirkpatrick was additionally made aware of his failure to file upon receipt of
the original Notice of Investigation letter dated May 28, 2008.
1. Kirkpatrick received the original Notice of Investigation letter on May
30, 2008.
82. Kirkpatrick did not file a Statement of Financial Interests for calendar year 2007
until April 15, 2009, when he also completed a Statement of Financial Interests for
calendar year 2008.
III. DISCUSSION:
Respondent James Kirkpatrick (hereinafter also referred to as "Respondent,"
"Respondent Kirkpatrick," and "Kirkpatrick ") was employed as a Transportation Facilities
Administrator 1 with the Pennsylvania Department of Transportation ( "PennDOT ") from
approximately July 13, 1999, through January 3, 2008.
Before addressing the allegations, we preliminarily note that in a Position Statement
filed June 23, 2009, the Investigative Division has indicated that it is no longer pursuing
the alleged violation of Section 1103(a) of the Ethics Act in this case. We conclude that
there has been a not pros of the Section 1103(a) allegation, and we need not address it
further.
The remaining allegations are that Respondent violated Sections 1104(a) and
1105(b)(4) -(5) of the Ethics Act, 65 Pa.C.S. §§ 1104(a) and 1105(b)(4) -(5), when he, as a
Transportation Facilities Administrator 1 for PennDOT, failed to file a Statement of
Financial Interests for the 2007 calendar year by May 1, 2008; when he failed to disclose
all direct /indirect sources of income on Statements of Financial Interests filed for the 2004
and 2005 calendar years; and when he failed to disclose the identity of all creditors on a
Statement of Financial Interests filed for the 2006 calendar year.
Section 1104(a) of the Ethics Act provides that each public official /public employee
must file a Statement of Financial Interests for the preceding calendar year, each year that
he holds the position and the year after he leaves it. The filing deadline is May 1.
Section 1105(b) of the Ethics Act and its subsections detail the financial disclosure
that a person required to file the Statement of Financial Interests form must provide.
Subject to certain statutory exceptions not applicable to this matter, Section
1105(b)(4) of the Ethics Act requires the filer to disclose on the Statement of Financial
Interests the name and address of each creditor to whom is owed in excess of $6,500 and
the interest rate thereon.
Subject to certain statutory exceptions not applicable to this matter, Section
1105(b)(5) of the Ethics Act requires the filer to disclose on the Statement of Financial
Interests the name and address of any direct or indirect source of income totaling in the
aggregate $1,300 or more.
We shall now summarize the relevant facts.
Respondent was employed by PennDOT as a Transportation Facilities
Administrator !from approximately July 13, 1999, through January 3, 2008. Respondent
was the Transportation Facilities Administrator I assigned to Engineering Districts 11 -0 and
12 -0.
Kirkpatrick, 08 -022
Page 26
The Position Description for the Transportation Facilities Administrator I for
Engineering Districts 11 -0 and 12 -0 defines the position purpose as participation in the
planning, assigning, directing, and coordinating of services associated with building
design, maintenance, construction, and repair for all facilities within Transportation
Engineering District 11 -0 and 12 -0 and includes, inter alia, the following duties and
responsibilities:
(1) Maintaining and managing district four -year facilities plans and
budgeting and ensuring that funding is spent wisely;
(2) Planning and coordinating services associated with building
maintenance, design construction, and repair district wide;
Developing specifications and scope of work for facilities projects and
services;
(3)
(4) Developing and completing initial contract bid documents and
associated ITQ contract requirements involved in the competitive
bidding process;
(5)
Directing the preparation of facility design, construction, renovation,
and demolition projects with input from agency consultative staff;
(6) Scheduling and conducting required project management meetings,
including pre -bid, pre -job, interim job, final inspection, and other
meetings as required;
Conducting inspections of project work sites and ensuring contractor
compliance and performance in accordance with contract
specifications and scope of work; and
(8) Evaluating project status and percentage of completion, and
processing contractor invoices and associated departmental forms
required for payment of invoices in a timely manner.
(7)
See, Fact Finding 13.
Respondent filed Statements of Financial Interests with PennDOT as detailed in
Fact Findings 78 -82.
Respondent failed to file his 2007 calendar year Statement of Financial Interests
with PennDOT by May 1, 2008. In May 2008 Respondent was made aware of his failure to
file the form, but Respondent did not file a Statement of Financial Interests for calendar
year 2007 until April 15, 2009.
Respondent failed to disclose the identity of his automobile creditor on his
Statement of Financial Interests filed for calendar year 2006. Respondent's Statement of
Financial Interests for calendar year 2006 documents only "Auto Loan," "Bal. 9300.00,"
and "6.5" (interest) under "Creditors." Respondent did not disclose the actual name of the
creditor or the address of the creditor as required by the Ethics Act.
Respondent has admitted that he failed to disclose all direct /indirect sources of
income on his Statement of Financial Interests filed for calendar year 2005. The admitted
Findings include that Respondent was employed with Sony Technology of Pittsburgh from
at least October 20, 2004, through April 20, 2005. Respondent disclosed income in the
amount of $5,500.00 from Sony Technology during the period of October 20, 2004,
through April 20, 2005, on another financial disclosure form required by the Governor's
Kirkpatrick, 08 -022
Page 27
Code of Conduct. Respondent did not disclose Sony Technology of Pittsburgh as a direct
or indirect source of income on his 2005 calendar year Statement of Financial Interests.
Having summarized the above relevant facts, we must now determine whether the
actions of Respondent Kirkpatrick violated Sections 1104(a) and 1105(b)(4) -(5) of the
Ethics Act.
We initially determine that as a Transportation Facilities Administrator I for
PennDOT from approximately July 13, 1999, through January 3, 2008, Respondent was a
public employee subject to the provisions of the Ethics Act, and in particular, the
requirements for filing Statements of Financial Interests pursuant to the Ethics Act. This
conclusion is based upon the job duties set forth at Fact Finding 13, which indicate clearly
that Respondent had the power /authority to take or recommend official action of a non -
ministerial nature with respect to activities where the official action had an economic
impact that was greater than de minimis on the interests of another person. For example,
Respondent had the power /authority to: manage district four -year facilities plans and
budget and ensure that funding was spent wisely; develop contract specifications, scopes
of work, initial contract bid documents, and contract requirements; conduct inspections of
project work sites; and ensure contractor compliance and performance in accordance with
contract specifications and scopes of work. Therefore, Respondent was a "public
employee" subject to the Ethics Act, and he was required to file Statements of Financial
Interests pursuant to the Ethics Act.
In applying the allegations to the facts of record, we hold that Respondent violated
Section 1104(a) of the Ethics Act when he failed to file a Statement of Financial Interests
for calendar year 2007 with PennDOT by May 1, 2008. Despite being informed in May
2008 of the delinquency of the form, Respondent did not file a Statement of Financial
Interests for calendar year 2007 until April 15, 2009.
We hold that Respondent violated Section 1105(b)(4) of the Ethics Act when he
failed to disclose the identity (name and address) of his automobile creditor on his
Statement of Financial Interests filed for calendar year 2006. Respondent provided some
information regarding the automobile loan, but he did not disclose the name or address of
the creditor as required.
Additionally, we hold that Respondent violated Section 1105(b)(5) of the Ethics Act
when he failed to disclose all direct /indirect sources of income on his Statement of
Financial Interests filed for calendar year 2005.
As for the allegation that Respondent failed to disclose all direct /indirect sources of
income on his Statement of Financial Interests filed for the 2004 calendar year, it appears
that the Investigative Division in the exercise of its prosecutorial discretion has elected to
non pros that particular allegation.
To the extent he has not already done so, Respondent is directed to file amended
Statements of Financial Interests with PennDOT for calendar years 2005 and 2006
disclosing all required information, and to forward copies of all such filings to this
Commission for compliance verification purposes by no later than the thirtieth (30) day
after the mailing date of this adjudication and Order.
IV. CONCLUSIONS OF LAW:
1. As a Transportation Facilities Administrator I for the Pennsylvania Department of
Transportation ( "PennDOT ") from approximately July 13, 1999, through January 3,
2008, Respondent James Kirkpatrick ( "Kirkpatrick ") was a public employee subject
to the provisions of the Public Official and Employee Ethics Act ( "Ethics Act "), 65
Pa.C.S. § 1101 et seq.
Kirkpatrick, 08 -022
Page 28
2. Kirkpatrick violated Section 1104(a) of the Ethics Act, 65 Pa.C.S. § 1104(a), when
he failed to file a Statement of Financial Interests for calendar year 2007 with
PennDOT by May 1, 2008.
3. Kirkpatrick violated Section 1105(b)(4) of the Ethics Act, 65 Pa.C.S. § 1105(b)(4),
when he failed to disclose the identity (name and address) of his automobile
creditor on his Statement of Financial Interests filed for calendar year 2006.
4. Kirkpatrick violated Section 1105(b)(5) of the Ethics Act, 65 Pa.C.S. § 1105(b)(5),
when he failed to disclose all direct /indirect sources of income on his Statement of
Financial Interests filed for calendar year 2005.
In Re: James Kirkpatrick,
Respondent
ORDER NO. 1519
File Docket: 08 -022
Date Decided: 7/8/09
Date Mailed: 7/10/09
1 Respondent James Kirkpatrick ( "Kirkpatrick "), a public employee in his capacity as
a Transportation Facilities Administrator I for the Pennsylvania Department of
Transportation ("PennDOT ") from approximately July 13, 1999, through January 3,
2008, violated Section 1104(a) of the Ethics Act, 65 Pa.C.S. § 1104(a), when he
failed to file a Statement of Financial Interests for calendar year 2007 with
PennDOT by May 1, 2008.
2. Kirkpatrick violated Section 1105(b)(4) of the Ethics Act, 65 Pa.C.S. § 1105(b)(4),
when he failed to disclose the identity (name and address) of his automobile
creditor on his Statement of Financial Interests filed for calendar year 2006.
3. Kirkpatrick violated Section 1105(b)(5) of the Ethics Act, 65 Pa.C.S. § 1105(b)(5),
when he failed to disclose all direct /indirect sources of income on his Statement of
Financial Interests filed for calendar year 2005.
4. To the extent he has not already done so, Kirkpatrick is directed to file amended
Statements of Financial Interests with PennDOT for calendar years 2005 and 2006
disclosing all required information, and to forward copies of all such filings to thus
Commission for compliance verification purposes by no later than the thirtieth (30
day after the mailing date of this Order.
BY THE COMMISSION,
Louis W. Fryman, Chair